Good afternoon. The work schedule for next week, 10/19-10/23, for the PSEG gas main project will again have two service crews and is as follows:

One crew

Monday, 10/19, and Tuesday, 10/20
Landis Ave from West Holly Ave to Kendall Blvd

Wednesday, 10/21, through Friday, 10/23
Bryant Ave from West Holly Ave to Kendall Blvd

Another crew

Monday, 10/19, and Tuesday, 10/20
Laurie Lane from Oaklawn Ave to the Dead End

Wednesday, 10/21, and Thursday, 10/22
Coldspring Ave from East Bettlewood Ave to East Beechwood Ave

Friday, 10/23
Oaklawn Ave from East Bettlewood Ave to East Beechwood Ave

Work hours are 7am to 5pm

Ask I police officer at the job site if you have any questions
about 1 month ago, Chad Jordan

Reminder- Tonight, Friday October 9th, the Oaklyn Green Team will be holding a Movie in the Park at the VFW Park. Come out and enjoy a screening of Fern Gully. Should begin around dusk, 6:45 p.m.

about 1 month ago, Bonnie Taft
October 2026 Council Meeting Agenda
about 1 month ago, Bonnie Taft
Due to the weather forecasted for Sunday, the Oaklyn Civic Association has decided to move the Town Picnic to next Sunday, October 18th. It will take place in front of the Oaklyn Public School from 12 p.m. to 3 p.m. Hopefully the weather will be better next Sunday.
about 1 month ago, Bonnie Taft
Good afternoon. PSE&G Gas Main Project work schedule for next week (10/12-10/16) will have two service crews and is as follows:

One Crew

Monday 10/12-Tuesday 10/13
West Holly Ave from Manor Ave to Landis Ave

Wednesday 10/14-Friday 10/16
Landis Ave from West Holly Ave to Kendall Blvd

Another Crew

Monday 10/12-Friday 10/16
Washington Ave from Harding Ave to the Dead End

Work hours are 7am - 5pm

As always, ask a police officer working the detail if any questions
about 2 months ago, Chad Jordan
The Camden County Mosquito Commission will be conducting ULV “spraying” operations on Friday, October 9 between the hours of 2am-6am in the following locations, weather permitting:

E. Lakeview Ave.
E. Beechwood Ave.
E. Bettlewood Ave.
Johnson Ave.
Oaklawn Ave.
White Horse Pike.
Coldsprings Ave.
Laurie Ln.
about 2 months ago, Bonnie Taft
Green Team Movie Night
about 2 months ago, Bonnie Taft

Oaklyn Town Picnic-Sunday, October 11- 12 p.m. to 3 p.m.

about 2 months ago, Bonnie Taft
October 2026 Planning Board
about 2 months ago, Bonnie Taft
Senior Center Event
about 2 months ago, Bonnie Taft
October 2026 Caucus Meeting Agenda
about 2 months ago, Bonnie Taft
Good afternoon. PSE&G gas main project work schedule for next week, 10/5-10/9, will have 2 service crews and is as follows:

One service crew

Monday 10/5-Friday 10/9
Manor Ave from Congress Ave to W Holly Ave

Another service crew

Monday 10/5 and Tuesday 10/6
Ridgeway Ave from Goff Ave to Washington Ave

Wednesday 10/7 to Friday 10/9
Washington Ave from Harding Ave to the Dead End

Work hours are 7am to 5pm

Any questions please ask a police officer in the work zone
about 2 months ago, Chad Jordan
The Camden County Mosquito Commission will be conducting ULV “spraying” operations on Friday October 2, 2026 between the hours of 2am-6am in the following locations, weather permitting:

Kendall Blvd.
W. Oakland Ave.
Walnut Ave.
Bryant Ave.
Landis ave.
W. Holly Ave.
about 2 months ago, Bonnie Taft
GREEN DAY-Saturday, October 10th
about 2 months ago, Bonnie Taft
October Senior Center Events
about 2 months ago, Bonnie Taft
Good evening. PSE&G gas main project work schedule for next week, 9/28-10/2, will have two service crews and is as follows: 1st Crew Monday 9/28 Spruce Ave from West Cedar Ave to West Holly Ave Tuesday 9/29 and Wednesday 9/30 Kendall Blvd from West Holly Ave to West Cedar Ave Thursday 10/1 and Friday 10/2 Kendall Blvd from West Park Ave to West Cedar Ave 2nd Crew Monday 9/28 - Friday 10/2 Ridgeway Ave from Goff Ave to Washington Ave Work hours are 7am - 5pm Any questions please ask the police officer working the job site
about 2 months ago, Chad Jordan

Attention Residents!

2 months ago, Bonnie Taft
Reminder to residents- Any type of lawn signs can not be placed on the curb strip. They must be placed on your lawn (private property)
2 months ago, Bonnie Taft
Good afternoon.
Work for the PSE&G Gas Main project for this upcoming week (9/21-9/25) is as follows:

There will be two service crews this week.

First crew

Monday, 9/21 - West Park Ave from Kendall Blvd to Maple Ave

Tuesday, 9/22-Thursday, 9/24 - Maple Ave from West Cedar to West Holly

Friday, 9/25 - Spruce Ave from West Cedar to West Holly

Second crew

Monday, 9/21-Friday, 9/25 - Ridgeway Ave from Harding Ave to Washington Ave

Work hours are 7am - 5pm

Any questions please ask the police officer in the work zone
2 months ago, Chad Jordan
Good morning. We received an email today from NJDOT’s consulting engineers informing us that they are starting the next phase of the Route 30 Cooper Street to Grove Street Project. This project is a six-mile pavement and infrastructure improvement effort that goes from Camden down to Haddon Heights along Route 30 (White Horse Pike). In the information listed below it states they are starting this work next Monday, 9/21, at the section of Magill Ave and Route 30 in Collingswood and working their way East on Route 30. As they move East they will be working towards Oaklyn so I wanted to notify every one of their plans as they will be in Oaklyn in the coming weeks. This information is also going out on our app, our website and our Facebook page. September 17, 2026 Starting Monday September 21, 2026, the Contractor will be entering the next phase of the Rt. 30 Cooper St. to Grove St. project. The Contractor will be starting intersection (underground) work on the White Horse Pike from Collingswood to Haddon Heights. The first intersection will be Magill Ave. and will continue east. The intersection work involves installation of electrical conduit, junction boxes and foundations for the future above ground electrical items (signal poles, controller cabinets, etc.) Portions of sidewalk and ADA ramps may need to be removed. Pedestrian access will be maintained and/or detoured while work is ongoing. The Contractor expects to be constructing underground electrical work for one to two weeks at each intersection.
2 months ago, Chad Jordan